Oregon DOT invites bids for US 26 construction project in Multnomah County. Work includes median island extension, concrete traffic separator, illumination pole installation, and permanent pavement markings. Bids due via OregonBuys by 12/03/2026 2:00 PM PST. No prebid conference. Bid security 10% required. Award to lowest responsive bidder. Project estimate $100,****,000. State funded. Prevailing wage rates apply. Liquidated damages apply. Substantial completion by 09/01/2027.
Substantial completion is September 1, 2027, and final completion is September 15, 2027, as stated: substantial completion: september 1, 2027final completion: september 15, 2027.
Payment will be based on actual measured quantities: payment will be made based on actual, measured quantities. No retainage will be withheld: agency will not withhold retainage.
Award will be made to the responsible bidder submitting the lowest responsive bid: award will be made to the responsible bidder submitting the lowest responsive bid.
Bidder must be registered in OregonBuys and licensed with the State Construction Contractors Board: bidder must be licensed with the state construction contractors board ccb prior to bidding on public improvement contracts.
Liquidated damages will apply for failure to complete by substantial completion date: liquidated damages will apply to the contract resulting from this itb for failure to complete the project by the substantial completion date.
Solicitation protests must be received 7 calendar days prior to bid opening: deadline for solicitation protests. . . 7 calendar days prior to the bid opening date identified in oregonbuys.
Bids may be rejected if nonresponsive, including taking exception to specifications or being unreadable: bids may be considered nonresponsive and rejected if the bid: includes nonapproved equivalents. . . or is unreadable.
Project cost estimate is $100,000 to $250,000: the following range is a project estimate for bonding purposes: 100, 000 to 250, 000.